Dual-Fuel Mobile Gas Turbines: How Gas-to-Liquid Fuel Changeover Works

A trailer-mounted gas turbine often goes to places where the gas supply is not guaranteed: a temporary connection, a lateral still under construction or a pipeline that can be curtailed. Dual-fuel capability gives the unit a second route to keep running, usually on liquid distillate. It sounds simple, but changing fuel on a running turbine is a controlled event with its own hardware, logic and risks.

This article explains how dual-fuel mobile units are arranged, how the changeover works, and what the project team should test and plan before the equipment leaves the yard. It is written for owners, site managers and operators who may be asked to approve a liquid fuel backup without having seen one in action.

Why specify dual fuel on a mobile unit

Mobile power is often chosen for speed, which means supporting infrastructure may be incomplete. A site may start on liquid fuel while the gas lateral is built, then move to gas when it is ready. Another may use gas as the normal fuel but keep liquid on standby in case of a curtailment. In both cases the second fuel is insurance for the output commitment.

Dual-fuel machines carry extra equipment: a liquid fuel forwarding skid, a fuel nozzle set suited to both fuels, atomising air or water systems on some designs, and controls that manage the transfer. That equipment adds weight, trailer count and commissioning work, so it should be justified by a real supply risk and not added by default. Our guide to mobile gas turbine fuel consumption helps size the tanks that follow from that decision.

The hardware behind the changeover

On gas, the combustor receives fuel through gas manifolds and nozzles. On liquid, fuel is pumped at high pressure to the same nozzles or to a separate set of liquid circuits, with a flow divider or control valves apportioning it evenly across the combustion cans. Check valves and block valves prevent one fuel from backing into the other’s system.

Because the liquid passages are idle when the turbine runs on gas, they must be protected from heat and from coking. Many designs purge them with compressed air or water while on gas, and drain or flush them after a liquid run. Details differ by manufacturer, so the operation manual for the specific unit is the final authority.

On-line and off-line transfer

Transfers are either on-line, with the turbine carrying load throughout, or off-line, with a stop and restart on the new fuel. On-line transfer is what most operators want, because it avoids an outage. The control system gradually reduces gas flow while increasing liquid flow, holding the total energy input steady so that power output and exhaust temperature stay within limits.

Typical transfers take place within a defined load range, since combustion stability is best understood and tested in that window. A transfer outside it may be blocked or may require load to be adjusted first. If the gas supply is lost suddenly, the control system can trigger an automatic emergency transfer, which is a harder event on the combustor. Teams should test this behaviour rather than assume it, and discuss the result with the manufacturer.

Combustion and emissions differences

Liquid fuel burns differently. Flame temperature, luminosity and the formation of nitrogen oxides all change. Dry low-emission combustors designed for gas may need water or steam injection to keep emissions within limits on liquid. If that is the case, the unit needs a demineralised water supply and an injection skid, which adds another trailer and another logistics item to the plan.

Permits should be written to cover both fuels, including any limit on hours on liquid. The mobile GT fuel quality field note explains the sampling that protects nozzles and hot-section parts; the same discipline applies even more strictly to distillate that has sat in a storage tank.

Fuel storage and logistics for the backup fuel

Liquid backup is a storage problem as much as a turbine problem. Runtime at full load is simply tank volume divided by consumption, so a quick calculation shows the cost of autonomy. As an illustration, if a unit burns 8,000 litres per hour at full load, a 100,000 litre tank gives about 12 hours of running. Supply trucks, unloading points and bunding must be planned around that number, and the tank needs a quality check before the first use.

Fuel left in tanks and lines for long periods ages, collects water and supports microbial growth. A routine for sampling, water draining and periodic circulation through a filter keeps the backup fuel usable. Spills are a real hazard on a temporary site, so containment, drip trays and hose management belong in the site plan alongside the turbine itself.

What to test before mobilisation

A changeover should be proven before the unit ships, ideally on a test bed or during site commissioning, and repeated at every new site. A simple test plan covers a planned on-line transfer from gas to liquid and back, an off-line start on liquid, an emergency transfer when gas is lost, and a check of purge and drain functions. Each test should have recorded pass criteria for load, exhaust temperature spread, vibration and any alarms.

Operator training matters just as much as hardware. Crews should know which permissives block a transfer, what to do when one fails, and how to confirm the idle fuel system is purged. Where the unit is part of a campus bridge power plan, the same checklists should sit alongside our overview of mobile turbine generators for temporary and bridge duty.

About the authors

This guide comes from the USP&E mechanical and controls engineers who commission fuel systems on gas turbine plants. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our work on the wider plant is described on our power plant EPC projects page.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Dual-fuel mobile turbine questions

What does dual fuel mean on a gas turbine?

The combustion system can burn natural gas or a liquid fuel such as distillate, with controls that allow the unit to switch from one to the other.

Can a turbine change fuel while it is running?

Many designs support on-line transfer within a defined load range, with gas reduced and liquid increased gradually, but the limits come from the manufacturer.

Why would a mobile turbine need liquid backup?

The gas connection may be temporary, incomplete or subject to curtailment, and liquid fuel keeps the unit running when the gas supply is lost.

Is water injection needed on liquid fuel?

Some dry low-emission combustors need water or steam injection on liquid fuel to meet emission limits, which adds a water supply and skid.

How long will a backup fuel tank last?

Divide the usable tank volume by the full-load fuel burn per hour. The result is the runtime at full load, which is shorter than many owners expect.

What should be tested before shipping the unit?

Planned transfers in both directions, an off-line start on liquid, an emergency transfer on loss of gas and the purge and drain functions of the idle fuel system.

Review your fuel changeover plan

Send the unit data sheet, fuel supply arrangement and permit conditions for your mobile turbine project, and our engineers will review the changeover logic, tank sizing and test plan.

Phone +27 10 822 2324 during office hours, or write to info@uspeglobal.com at any time; the fuel system enquiry also routes straight to our project engineers. Gas turbine units for temporary and bridge duty are listed in our gas turbine inventory.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · Mobile Gas Turbine Generators is part of USP&E

Categories:

Tags:

No responses yet

Leave a Reply

Your email address will not be published. Required fields are marked *