Adding a battery energy storage system beside the turbines changes that picture. This guide explains what the battery does on a mobile turbine site, how its power and energy are sized, how the controls hold the two together, and when a battery adds little enough that it is better left out.
Why turbines need help with load steps
Aeroderivative turbines respond quickly compared with large frame machines, but every turbine has a limit on how much load it can pick up in one step without a large frequency dip. That limit is lower in hot weather, at altitude and at light load, and it is lower again on a site with no grid connection to lean on. Our article on hot ambient derate for mobile turbines shows how quickly margins shrink on hot days.
Data center loads make this harder. IT halls are commissioned in blocks, mechanical plant starts large motors, and some compute workloads swing sharply within seconds. Without support, the site has to run extra turbines lightly loaded just to absorb these swings, which burns fuel and adds wear.
What the battery actually does
On a hybrid site the battery has four main jobs. It absorbs load steps in the first seconds, while turbine fuel controls catch up. It provides fast reserve, so the loss of one turbine is covered while the others ramp up. It can carry the site briefly while a turbine starts, which lets the plant keep fewer units spinning. And it smooths small fluctuations, so the turbines run at steadier output.
None of these roles needs a very large energy store. They depend on power, delivered within a fraction of a second, for a few minutes at most. That is what keeps a hybrid practical on a mobile site, where space and road transport limit what can be brought in.
Sizing power and energy
Start with the largest event the battery must cover. If a site runs four turbines of 30 MW each and must survive the trip of one, the battery needs roughly 30 MW of power to hold the load while the others ramp up. If the others need around five minutes to take the load, the energy required is about 30 MW multiplied by one twelfth of an hour, or 2.5 MWh, plus a margin for ageing and for the state of charge it must keep in reserve.
Check the largest load step separately. If an IT block of 15 MW comes on at once, the battery power rating must cover that too. The final rating is the larger of the two cases, with energy set by how long the turbines need to respond. These figures are illustrative arithmetic, not a design; real sizing follows a dynamic study of the actual units and loads.
Grid-forming inverters and the plant controller
Older battery systems follow the voltage and frequency set by the generators. On an islanded mobile site, a grid-forming inverter is usually preferred, because it holds voltage and frequency itself and responds to a disturbance instantly rather than after a measurement delay. That behaviour is what makes the battery useful in the first seconds of an event.
A plant controller sits above the turbines and the battery. It decides how many turbines run, sets their loading, keeps the battery within its state-of-charge band and starts another unit when reserve falls. It normally lives in, or connects to, the control trailer on a mobile site, and its logic needs testing with real load steps during commissioning.
Protection and fault current
Inverters supply far less fault current than a synchronous generator, often little more than their rated current. On a hybrid site that is fine while the turbines are running, but the protection study must check what happens if the battery is carrying the site alone during a turbine restart. Relays that need high fault current to operate may not trip on a downstream fault in that state.
The usual answers are to keep at least one turbine online whenever the site carries load, to use protection that works on low fault current, or both. These choices should be settled before the synchronising scheme for the packages is finalised, because the two interact.
Layout and fire separation
Battery containers arrive on the same kind of trucks as the turbine trailers and need a level, drained pad with cable routes to the medium voltage switchgear. Lithium-ion systems require separation from the turbines, fuel gas skids and fuel oil storage according to the applicable fire code and the battery manufacturer’s guidance, along with access for fire crews on more than one side.
Treat the battery as part of the site fire strategy, not an add-on. Detection, ventilation, explosion venting where required and an emergency response plan for thermal runaway belong in the same document as the turbine enclosure systems. Our page on fire protection for mobile turbine sites covers the turbine side.
When a battery is not worth adding
A battery adds equipment, interfaces and commissioning time. If the site has a firm grid connection that can absorb load steps, if the load is steady and well forecast, or if the bridge period is only a few months, the benefit may be small. Running one extra turbine as reserve can be simpler, particularly when it is already on site for redundancy.
The case for a battery is strongest on islanded sites with large or fast load swings, high fuel costs, emissions limits that reward running fewer units or a long bridge period. Our page on hybrid power system design sets out how storage is combined with thermal generation more generally.
Planning for the move to permanent power
Bridge power is temporary by definition. When the permanent plant or grid supply arrives, the mobile turbines leave, but the battery may still be useful. It can stay to support the permanent plant with load steps and reserve, or move with the turbines to the next site.
Decide this early. A battery that will stay should be sited and connected where the permanent switchgear will be, while one that will move should be built on transportable skids with plug-in cable connections. Our guide to bridge power for data centers explains how the wider transition is staged.
About the authors
This guide comes from the USP&E mobile power and hybrid systems engineering team. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our approach to powering compute campuses is described on the data centre power page.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Turbine and battery hybrid questions
Why pair a mobile gas turbine with a battery?
The battery absorbs sudden load steps, covers a turbine trip while the others ramp up and lets the site run fewer turbines as reserve.
How large does the battery need to be?
Usually sized on power, enough to cover the largest turbine trip or load step, with energy for the few minutes the turbines need to respond.
Does the battery need grid-forming inverters?
On an islanded site, grid-forming inverters are usually preferred because they hold voltage and frequency instantly during a disturbance.
Can the battery run the site on its own?
Only briefly, and protection must still work with the lower fault current inverters supply. Many sites keep at least one turbine online.
Is a battery always worth adding to mobile turbines?
No. With a strong grid connection, steady loads or a short bridge period, an extra turbine as reserve may be simpler.
What happens to the battery after bridge power ends?
It can stay to support the permanent plant or move with the turbines, which should be decided before it is sited and connected.
Plan a hybrid bridge site
Send the expected load profile, block start schedule and site constraints, and our engineers will outline a turbine and battery arrangement with the studies it needs.
Phone +27 10 822 2324 during office hours, or write to info@uspeglobal.com at any time; the mobile power enquiry page also routes straight to our project engineers. Trailer and skid packages are listed in our turbine inventory.
No responses yet