This guide walks through the exit from a site and the move to the next: shutdown, preservation, disconnection, transport, inspection and recommissioning. It is written for owners, project managers and operators planning a fleet of mobile units that will move between bridge power, outage cover and peak support jobs.
Plan the exit before the last shutdown
Demobilisation deserves a written plan prepared weeks before the final run. It should name the shutdown date, the preservation method, the crane and transport bookings, the people who will isolate the gas and electrical connections, and the condition in which the site must be returned. The mobilisation plan used to arrive is a useful template, because most of its steps run in reverse; our mobilisation timeline notes list them.
Agree with the next project whether the unit will go straight there or pass through a workshop first. That decision shapes how thorough the preservation needs to be and whether parts should be ordered in advance.
Final shutdown and preservation
Run the unit through a normal shutdown and full cool-down, with the lube oil system circulating as the manufacturer requires. Record final readings of vibration, exhaust temperature spread and oil condition; they become the baseline for the next site and help separate transit damage from wear that already existed.
- Seal the air inlet and exhaust openings against rain, dust and animals.
- Drain or preserve the liquid fuel system if the unit has dual fuel capability, so distillate does not age in the lines.
- Place desiccant where the manufacturer recommends and fit humidity indicators that can be read without opening the enclosure.
- Apply the engine and generator preservation steps in the operation manual, including any periodic rotation for long storage.
- Take an oil sample and record filter differential pressures before anything is disconnected.
Preservation records matter later. If the unit sits for months between sites, the next team needs to know what was done and when it must be repeated.
Disconnection and site restoration
Electrical isolation follows the utility or site owner’s switching programme. Once the connection is proven dead, cables between the generator trailer, the control trailer and the step-up transformer are removed, coiled and tagged so they can be reused. Gas isolation needs equal care: the lateral is closed at the agreed point, the plant side is depressurised and purged to a safe atmosphere, and blind flanges are fitted before anyone opens a joint.
Close out the paperwork as well as the hardware. Emissions and operating permits may need final reports, waste oil and filters must be removed by licensed handlers, and the ground should be restored to the condition agreed in the site preparation scope described in our site preparation guide.
Transport and route checks
Mobile turbine trailers are heavy and tall, so the route out may not be the route in if bridges, roadworks or seasonal restrictions have changed. Confirm permits, escort requirements and the order in which trailers leave so each arrives at the next site in the sequence it will be installed.
Secure loose items inside enclosures, check tyre condition, brakes and lights on every trailer, and photograph the unit before it moves. Those photographs, together with the final readings taken at shutdown, make any transit damage claim straightforward.
Pack the ancillary equipment with the same care as the turbine. Fuel forwarding skids, water injection skids, cable reels, spare filters, special tools and the site office containers all need an inventory and a place in the convoy. Missing a single torque tool or protection relay test set at the next site can hold up first fire for days, so the packing list should be checked off at both ends of the journey.
Inspection between sites
The interval between projects is the best time to look inside. A borescope inspection of the hot section, a review of operating hours and start counts against the maintenance plan, inlet filter replacement and a lube oil analysis can all be done without pressure from a waiting customer. If the hours suggest a major event is near, it is usually better to do it now than at the next site.
Some fleets swap the gas generator or power turbine module during this window rather than in the field. Our article on engine change-out for mobile units explains when that makes sense.
Recommissioning at the new site
The new site brings new conditions: a different grid, protection settings, ambient temperature, altitude and gas supply. Review each before the unit arrives. Protection relays must be set for the new connection, and the generator frequency and voltage must match the local system or be matched through the transformer and switchgear. Gas composition and pressure need checking against the turbine limits again, because a new pipeline is not the same as the old one.
Recommissioning then follows a shortened version of first commissioning: remove preservation, inspect, check auxiliaries, run lube oil and fuel systems, carry out a first fire, synchronise, and load step by step. Trailer mounted aeroderivative units are built for this cycle; the GE TM2500 explainer shows how one widely used design approaches it. For a broader view of where these units fit, see our overview of mobile turbine generator options.
About the authors
This guide comes from the USP&E field engineers who mobilise, operate and move gas turbine units between project sites. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our site support scope is described on our operations and maintenance page.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Mobile turbine redeployment questions
How is a mobile gas turbine prepared for a move?
It is shut down and cooled normally, inlet and exhaust are sealed, fuel systems are drained or preserved, desiccant is placed and final readings are recorded.
Does a mobile turbine need preservation between sites?
Yes, especially if it will sit for weeks or months. The manufacturer’s preservation steps protect the engine, generator and fuel systems from corrosion.
What should be inspected between deployments?
A hot section borescope, hours and start counts against the maintenance plan, inlet filters and a lube oil analysis are common checks.
Can a mobile unit run on a different grid frequency?
The generator runs at its design frequency, so the new site must match it or the connection must be designed accordingly. Check this before the move.
How is the gas connection made safe?
The lateral is isolated at an agreed point, the plant side is depressurised and purged, and blind flanges are fitted before joints are opened.
Why record readings at the final shutdown?
They set a baseline for the next site and help show whether any later issue came from transport or already existed.
Plan your next redeployment
Send the unit details, current site arrangements and the next project location, and our field engineers will help plan preservation, transport checks and recommissioning.
Phone +27 10 822 2324 during office hours, or write to info@uspeglobal.com at any time; the mobile power enquiry also routes straight to our project engineers. Mobile and packaged turbine units are listed in our gas turbine inventory.
No responses yet