Trailer-mounted gas turbines are one practical way to cover those curtailment hours, either as a long-term solution or while permanent on-site generation is built. This guide explains how such an arrangement is sized, controlled and fuelled, and the questions to resolve with the utility before signing.
Why utilities offer curtailable connections
Transmission and generation capacity is planned for the few hours of highest system demand. A new campus that agrees to reduce its grid draw in exactly those hours adds far less strain than one that insists on full supply at all times. Utilities can therefore connect it sooner, sometimes with fewer network upgrades.
The terms vary. Some agreements cap the number of curtailment events or hours per year; others allow the utility to request a reduction to a fixed level at short notice. Read them as an operating specification, because they define exactly what the on-site plant must deliver.
Sizing to the curtailed block
The on-site plant does not usually need to carry the whole campus. It needs to carry the difference between the facility’s demand and the reduced grid limit during an event. If a campus draws 120 MW and the agreement allows the utility to cut it to 60 MW, the turbines must cover 60 MW plus a margin for redundancy and hot weather derate.
Mobile units are rated at specific ambient conditions. On a summer afternoon, which is when curtailment is most likely, output can fall noticeably. Size with hot-day figures and add at least one spare unit so a single trip does not leave the campus short.
Start time and notice periods
Agreements set how much warning the utility gives before an event. Aeroderivative mobile units can typically reach full load within minutes once started, but the plant still needs time to start, synchronise and take load in a controlled way. Match the notice period to a realistic start and loading sequence, including time for operators to confirm the plant is ready.
If the agreement allows very short or no notice, the campus may need a battery or the existing standby diesel fleet to carry the step while turbines start. Our page on turbines for data center peak demand covers the related case of daily peaks.
Controls and utility signals
The utility usually sends a dispatch signal or a set point through a secure telemetry link. The site controller must translate that into turbine starts, load ramps and a controlled reduction in grid import, while keeping voltage and frequency stable for the IT load. That logic should be tested with the utility before the first real event.
The turbines run in parallel with the grid during an event, so protection settings, synchronising equipment and export limits must be agreed. Our guide to synchronising mobile turbine packages explains the equipment involved.
Fuel supply for occasional running
Curtailment events are infrequent but can cluster during a heatwave. A pipeline gas connection is ideal, but some campuses start with trucked compressed or liquefied gas, or with dual-fuel units that can burn distillate. The fuel arrangement must cover the longest plausible run of events, not the annual average.
Gas supply contracts for a plant that runs only a few hundred hours a year need careful structuring. Interruptible gas that is cut during the same cold or hot spell that triggers curtailment would defeat the purpose.
Emissions permits and run-hour limits
Many air permits for on-site generation cap annual run hours or emissions. A plant intended for curtailment cover should be permitted for the maximum hours the agreement could require, plus testing. Mobile turbines with water injection or selective catalytic reduction can meet tighter limits than older standby engines.
Permitting can take longer than the equipment delivery, so start early. Our post on permitting mobile turbine fleets lists the documents regulators usually ask for.
Questions to settle with the utility
Before signing, confirm how many events and hours per year the utility may call, the notice period, the reduced import limit, and what happens if the campus cannot meet a request. Ask whether events are more likely in summer, winter or both, and whether the utility will share historical data on system peaks.
Clarify metering, telemetry standards and who pays for the communication link. Check whether the on-site plant may export power or must stay behind the meter. Finally, agree how the arrangement will be reviewed as network upgrades are completed, since some curtailable connections convert to firm supply after a few years.
The answers also shape the choice of technology. Where events are frequent and long, some owners compare turbines with engines, and our turbine and reciprocating engine comparison sets out the trade-offs.
Moving to permanent on-site generation
Mobile turbines are often the first step. Once the campus grows, the owner may install a permanent plant on site that covers curtailment, provides prime power and earns revenue in grid markets. The mobile units then move to the next site or remain as reserve.
Planning for that transition early saves rework. Fixing the substation layout, gas header and control architecture for the final plant lets the mobile fleet plug in now and the permanent units follow without rebuilding the yard.
About the authors
This guide comes from the USP&E gas turbine and data center power engineering team. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our broader view of turbine plants for compute campuses is in the article on gas turbine plants for data centers.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Data center curtailment questions
What is a curtailable data center grid connection?
A utility connection that is firm most of the time but allows the utility to reduce the campus’s grid draw during a limited number of peak or emergency hours each year.
How large should mobile turbines be for curtailment cover?
Large enough to carry the difference between campus demand and the reduced grid limit on a hot day, plus at least one spare unit for redundancy.
Can mobile gas turbines start in time for a curtailment event?
Usually, if the notice period allows for start, synchronising and controlled loading. With very short notice, batteries or standby diesel sets may bridge the first minutes.
Do turbines run in parallel with the grid during an event?
Typically yes, which means protection, synchronising and export settings must be agreed with the utility and tested.
What happens to the mobile units later?
They are often replaced by a permanent on-site plant as the campus grows, then moved to another site or kept as reserve.
Assess curtailment cover for your campus
Send the draft connection terms, campus load profile and site gas options, and our engineers will size a turbine arrangement and outline the controls and permits needed.